by David Millard | Feb 22, 2018 | Appeal, Engineering, Infrastructure, Steam
As of the 18th of February 2018 the second phase of the shed project has made rapid progress. In the three weeks since the last of the foundation pads were poured, all 12 of the uprights have been installed along with two of the roof girders and the outer roof wooden...